The City of West Columbia, South Carolina will receive Sealed Bids for the Saluda Gardens Water System Improvements Project – Divisions I and II until 2:00 PM on Thursday, December 9, 2021 in the New Brookland Room at West Columbia City Hall, 200 North 12th Street, West Columbia, SC 29169 at which time and place all Bids will be publicly opened and read aloud.

A Mandatory Pre-Bid Conference for Divisions I and II will be held on Wednesday, the 17th day of November 2021 at 2:00 PM in the New Brookland Room at the West Columbia City Hall, 200 North 12th Street, West Columbia, SC 29169.

Bids are invited upon the several items and quantities of work as follows:

Division I: Construction of approximately 13,000 linear feet (LF) of 6-inch and 4,345 LF of 2-inch water line; bore 496 LF of 2-inch water line, bore and jack 40 LF of 12-inch steel casing with 6-inch carrier pipe; installation of gate valves, fire hydrant assemblies, restrained joint fittings and air release valves; connections to existing water lines; installation of new service lines to existing water meters; abandonment of existing water lines and valves; removal and replacement of asphalt roadway, asphalt and concrete driveways, and concrete sidewalks; and all other necessary appurtenances as specified and depicted in the Contract Documents.

Division II: Construction of approximately 14,940 linear feet (LF) of 6-inch, 78 LF of 4-inch and 3,105 LF of 2-inch water line; bore 45 LF of 2-inch water line; installation of gate valves, fire hydrant assemblies, restrained joint fittings and air release valves; connections to existing water lines; installation of new service lines to existing water meters; abandonment of existing water lines and valves; removal and replacement of asphalt roadway, asphalt and concrete driveways, and concrete sidewalks; and all other necessary appurtenances as specified and depicted in the Contract Documents.